Q
If an actual price of material is $700 and the budgeted price is $900, then the ___________?
-
A
A. Cost variance is favorable
-
B
B. Cost variance is unfavorable
-
C
C. Price variance is favorable
-
D
D. Price variance is unfavorable
Correct Answer:
C. C. Price variance is favorable