Q If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
  • A A. 3.5 and 5/6
  • B B. 5 and 25/36
  • C C. 3.5 and 25/36
  • D D. 4 and 5/6