Q For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?
  • A A. Dry rolling, wet rolling, application of screening and application of filler
  • B B. Dry rolling, application of filler, wet rolling and application of screening
  • C C. Dry rolling, application of screening, wet rolling and application of filler
  • D D. Dry rolling, application of screening, application of filler and wet rolling