Q Clay layer A with single drainage and coefficient of consolidation Cv takes 6 months to achieve 50% consolidation. The time taken by clay layer B of the same thickness with double drainage and coefficient of consolidation Cv/2 to achieve the same degree of consolidation is_________________?
  • A A. 3 months
  • B B. 6 months
  • C C. 12 months
  • D D. 24 months