Mathematics Mcqs
Q C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
  • A A. 10 days
  • B B. 12 days
  • C C. 8 days
  • D D. 9 days