Q A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in_______days.
  • A A. 5 5⁄11
  • B B. 4 5⁄11
  • C C. 6 4⁄11
  • D D. 6 5⁄11