Q A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
  • A A. 4(2/3) days
  • B B. 4 days
  • C C. 5(1/3) days
  • D D. 1(1/3) days