Which of the following is not achieved by an automated estimation tools ?
A. Predicting staffing levels
B. Predicting software cost
C. Predicting software schedules
D. Predicting clients demands
What is related to the overall functionality of the delivered software ?
A. Function-related metrics
B. Product-related metrics
C. Size-related metrics
D. None of the mentioned
CLSS stands for_____________________?
A. Conveyor line sorting system
B. Conveyor line sorting software
C. Conveyor line sorting speed
D. Conveyor line sorting specification
Which of the following costs is not part of the total effort cost ?
A. Costs of networking and communications
B. Costs of providing heating and lighting office space
C. Costs of lunch time food
D. Costs of support staff
Which technique is applicable when other projects in the same analogy application domain have been completed ?
A. Algorithmic cost modelling
B. Expert judgement
C. Estimation by analogy
D. Parkinson’s law
Which of the following states that work expands to fill the time available ?
A. Case tools
B. Pricing to win
C. Parkinson’s law
D. Expert judgement