Removal of ______________ is accomplished by aeration of water?
A. Dissolved gases
B. Suspended solids
C. Dissolved solids
D. None of these
Coal washing waste water containing about 3% suspended solids (comprising of clay, slate, stone etc.) is treated for solid particles removal ?
A. By chemical coagulation
B. In sedimentation tanks equipped with mechanical scrapper
C. In vacuum filter
D. In clarifiers
Suspended solid present in the waste water generated in blast furnace gas cooling and cleaning plant is removed by__________________?
A. Biological oxygen pond
B. Radial settling tank (thickener) using coagulant (lime & ferrous sulphate)
C. Lagoons
D. Filtration
Main pollutants released from iron & steel industry is__________________?
A. Co, co2 & so2
B. H2s, no & so3
C. Co2, h2s & no2
D. So3, no2 & co2
The major reason of hydrodynamic noise (i.e., noise resulting from liquid flow) is_________________?
A. Pipe vibrations
B. Cavitation
C. Boundary layer separation
D. Fluctuation in liquid flow